Key Milestones

Key Project Milestones

Start

Finish

Site Mobilization

August 2009

N/A

Site Clearing, Rough Grading

August 2009

Dec 2009

Site Services

Phased

N/A

Temporary Parking Lots

August 2009

January 2010

Bulk Excavation

December 2009

July 2010

Underground Services

December 2009

Jan 2010

New Main Entrance Opens in Existing Facility (off of Broadview Ave)

December 2009

N/A

St. Matthews Road Closed to Normal Traffic

January 2010

Spring 2013

New Hospital Construction Begins

January 2010

Spring 2013

Building Envelope

June 2011

April 2012

Concrete Structure

August 2010

October 2011

Interior Finishes

March 2011

September 2012

Renovate Don Jail

May 2010

December 2012

Demolition (Toronto Jail)

April 2013


Demolition (Existing Hospital)

April 2013

Fall 2014

Substantial Completion

N/A

February 2013

Patients Move into New Hospital:

N/A

April 2013

Build New Civic Courtyard

June 2013

December 2013

  Construction Hotline
416-461-8252
Ext. 2663

  Click to E-mail Us

Construction Hotline
416 305 1663
Click to Email Us

Latest News
PCL Work Communication Report No. 27 May - August 2013
08/05/2013
The purpose of this report is to provide information on upcoming construction activities at the Bridgepoint Hospital Redevelopment Project.
 
Jack Layton Way & Broadview Avenue Lane Closures
08/05/2013
From approx. May 13, 2013 to May 31, 2013 Jack Layton Way will be restricted to oneway traffic eastbound from St. Matthews Road to Broadview Avenue.
 
Join us! Riverdale-Bridgepoint Redevelopment Liaison Committee Meeting
05/11/2012
November 13, 2012 at 7 p.m.
Holy Eucharist Church, 515 Broadview Avenue, Toronto

The Riverdale-Bridgepoint Redevelopment Liaison Committee Meeting provides a forum for community organizations and neighbours in the immediate vicinity of Bridgepoint to be updated on and to discuss the progress of the construction of the new Bridgepoint Hospital.
 
For more information, please call 416-461-8252 x2663