Start

Finish

Site Mobilization

August 2009

N/A

Site Clearing, Rough Grading

August 2009

Dec 2009

Site Services

Phased

N/A

Temporary Parking Lots

August 2009

January 2010

Bulk Excavation

December 2009

July 2010

Underground Services

December 2009

Jan 2010

New Main Entrance Opens in Existing Facility (off of Broadview Ave)

December 2009

N/A

St. Matthews Road Closed to Normal Traffic

January 2010

Spring 2013

New Hospital Construction Begins

January 2010

Spring 2013

Building Envelope

June 2011

April 2012

Concrete Structure

August 2010

October 2011

Interior Finishes

March 2011

September 2012

Renovate Don Jail

May 2010

December 2012

Demolition (Toronto Jail)

April 2013

June 2013

Demolition (Existing Hospital)

April 2013

June 2013

Substantial Completion

N/A

February 2013

Patients Move into New Hospital:

N/A

April 2013

Build New Civic Courtyard

June 2013

December 2013

  Construction Hotline
416-305-1663
  Click to E-mail Us

Construction Hotline
416 305 1663
Click to Email Us

Latest News
Read the January 2012 issue of our redevelopment community newsletter
16/01/2012
The January 2012 issue of our redevelopment community newsletter, Changing the Landscape, is now available.
Map of construction truck routes
26/04/2010
View a map of the routes that construction trucks will take.
View our live webcams!
22/01/2010
Take a peek inside our construction site through our three webcams.