Key Project Milestones
Start
Finish
Site Mobilization
August 2009
N/A
Site Clearing, Rough Grading
Dec 2009
Site Services
Phased
Temporary Parking Lots
January 2010
Bulk Excavation
December 2009
July 2010
Underground Services
Jan 2010
New Main Entrance Opens in Existing Facility (off of Broadview Ave)
St. Matthews Road Closed to Normal Traffic
Spring 2013
New Hospital Construction Begins
Building Envelope
June 2011
April 2012
Concrete Structure
August 2010
October 2011
Interior Finishes
March 2011
September 2012
Renovate Don Jail
May 2010
December 2012
Demolition (Toronto Jail)
April 2013
June 2013
Demolition (Existing Hospital)
Substantial Completion
February 2013
Patients Move into New Hospital:
Build New Civic Courtyard
December 2013